Dani Farmer in a hi-vis vest checking the timber frame of a new extension, bushland beyond

Our workSunshine CoastExtension at frame stage

Guide

What a house extension costs on the Sunshine Coast, and what actually moves the price.

This guide does not publish a price list, because an extension is priced from the house it joins, the block it sits on and the plans it is built from. What it does is explain what moves the number, so the price you get after a site visit makes sense.

In short

  • The rooms inside an extension matter more than its size, because kitchens and bathrooms carry far more work than bedrooms.
  • Joining the new work to the old roof, floor levels and cladding is often the hardest part of the job.
  • A second storey is priced on what the ground floor needs to carry it, so engineering comes before the quote.
  • Prime cost and provisional sum allowances show which parts of a fixed price depend on your choices or on hidden conditions.

Size, shape and what goes inside

Floor area is the first thing people ask about, but on its own it tells you little. A simple rectangular room under a single roof plane is far less work than the same area wrapped around two sides of the house with a hip roof to tie in. What goes inside matters even more. A bedroom is a frame, linings, a window and paint. A kitchen or ensuite adds plumbing, drainage, waterproofing, joinery, tiling and extra electrical, all packed into a small footprint.

What makes the same floor area more work

  • Wet rooms such as a kitchen, ensuite or laundry inside the new space
  • A complex roof shape that meets the existing roof at several points
  • Wide openings and stacking doors that need engineered beams over them
  • Raked ceilings, which change the roof framing and often need engineering
  • Reworking existing rooms so the old and new layouts work together

Footings, structure and the site

Every extension starts in the ground. On a flat block with good soil, a slab or a simple set of footings goes in quickly. On a sloping hinterland block, reactive clay or a site with fill, the engineer may call for deeper footings, piers or a suspended floor. Highset and older timber homes often need the new floor built up on stumps so the levels line up with the existing rooms, which changes the structure entirely.

Access is the other half. A clear side path that a small excavator and a concrete pump can use makes for a quicker job than a narrow gap, a steep driveway or a pool between the street and the work. Where materials must be carried by hand or lifted by crane, the program and the labour reflect it. Trees, retaining walls, stormwater and a sewer line under the new footprint all have to be dealt with too.

The house you are joining

An extension is never only new work. The existing roof is opened to tie in the new one, a wall is removed or moved to connect the rooms, and floors, ceilings and finishes are made good where old meets new. In older homes, opening up a wall can reveal tired wiring, a switchboard that cannot carry new circuits, plumbing that needs rerouting, termite or water damage, or asbestos in old linings and eaves. None of that is visible from the yard, which is why the quote follows a walk through the house, the roof space and the subfloor.

Second storey additions

Building up is a different job from building out. The ground floor has to carry a new storey, so an engineer assesses the footings, the stumps or slab and the frame before anything is priced. Some houses need footings strengthened, new posts or steel inside the walls. The roof comes off, so the house has to be kept weathertight while the new floor goes on, and the stairs take space from the rooms below. Sometimes building out is the better answer, and we will say so.

What drives the price of going up

  • The engineer's findings on the footings, stumps and existing frame
  • Whether the whole roof comes off or only part of it
  • Scaffolding, weather protection and how long the house is opened up
  • Where the stairs land and what they take from the ground floor
  • Running plumbing, drainage and electrical up to the new level
  • Whether you can stay in the house through the main structural stages

Selections, approvals and engineering

Windows and doors are one of the biggest choices in any extension. Aluminium or timber, standard sizes or custom, a single door or a wall of stacking panels, each changes the number. So do cladding, roofing, flooring, the kitchen and bathroom fit-out and the lighting plan. On the paperwork side, an extension needs a building approval, and some blocks also need planning approval because of the planning scheme or an overlay such as flood, bushfire or steep land. Engineering, energy efficiency assessment and, where needed, a town planner are all part of the price.

How a fixed price is reached

We only build extensions on a fixed-price QBCC contract. The scope in the plans and specification is priced in full, and the price only moves if the scope does. Two kinds of allowance cover what cannot be fixed on day one. A prime cost allowance is a sum for an item you have not chosen yet, such as tapware, tiles or an oven, and the difference is adjusted once you choose. A provisional sum covers work that cannot be measured until the house is opened up, such as hidden rot or a sewer line in the way.

To get a real number, start with plans. If you have an architect's or designer's drawings, we quote from them; if not, we work with local designers who can draw them as the first stage. Dani visits, looks at the house, the block and the access, and talks through what you want and what it will take. Every allowance is explained line by line before you sign.

Questions

Quick answers.

Why is there no rough price for an extension?

Because two extensions with the same floor area can involve very different work. One may be a bedroom on a flat slab with easy access, the other a kitchen on a sloping block tied into an old roof. A figure given before seeing the house is a guess, and guesses tend to turn into variations. Plans and a site visit give a number you can rely on.

Is a second storey more involved than building out?

Usually, because the ground floor has to be engineered to carry it, the roof comes off and stairs are added. On a small or steep block, though, building up can be the only way to get the space. An engineer's assessment of the existing structure decides whether it is practical, and the price is built from that assessment.

What usually adds to an extension once it starts?

On a fixed-price contract, the agreed scope does not change unless you change it. Extra cost usually comes from something hidden: rotten framing, termite damage, asbestos or services in the wrong place. Those risks are identified at the site visit and carried as provisional sums, so there is already a line for them in the contract rather than a surprise.

Can a simpler design keep the price down?

Yes. A roof that meets the existing roof cleanly, standard window and door sizes, and wet rooms placed near existing plumbing all reduce work. So does keeping the parts of the old layout that already work. We talk through these choices with you and your designer before the plans are finalised, when changes are easy to make.

Start here

Tell us about the project.

Takes two minutes. If it fits what we do, we call you to arrange a site visit. If it does not, we will say so straight away rather than waste your time.

  1. 01You send the formSuburb, scope and a budget range are enough to start.
  2. 02We call within a business dayA Farmer Constructions team member rings for a short conversation about the house, the block and what you are after.
  3. 03Site visitWe walk it together and talk through the realistic path to a fixed price.
07 5492 9409 Monday to Friday, 7:30am to 3:30pm

Plan my project

A few details and a Farmer Constructions team member calls you back within a business day.

Add your name so we know who to call.
Add a phone number for the call back.
Enter an email address we can reply to.
Which suburb is the house in?
Pick the closest match.
A rough range is fine. It helps us plan the right first conversation. Choose the range closest to your budget.

Sent straight to Farmer Constructions. No newsletters, no sharing your details.

Thanks, it is on its way.

A Farmer Constructions team member will call you within a business day to talk through the project and arrange a site visit.

This one is probably not us.

At that budget a single-trade specialist will usually serve you better and cost less than a licensed builder with a certifier and a fixed-price contract.

If the scope might grow, or you are not sure what it will cost, call and we will talk it through.

Call 07 5492 9409

Ready to see what the house could become?

Send the form or call. Either way the next step is a conversation about your house, not a sales call.

Call Get a quote