In short
- Keeping the toilet, shower and basin where they are saves plumbing work, while moving them changes the job under the floor.
- Waterproofing is the part you never see and the part that fails first, so it goes to a licensed waterproofer.
- A shower niche is far easier to build into a new wall than to cut into an old one later.
- Hidden water damage, rot and asbestos are carried as a provisional sum, so a discovery already has a line in the contract.
Layout: keep it or change it
The biggest single decision is whether the layout stays. If the shower, toilet, vanity and bath stay roughly where they are, the plumber works with the existing drainage. Moving the toilet, or turning a bath into a walk-in shower on the far wall, means new drainage, and on a slab that can mean cutting the floor. Combining rooms, or borrowing space from a hallway or linen cupboard, adds framing and often a wall change the certifier needs to look at.
Before you decide, spend a few weeks looking at bathrooms you like and write a short list: shower, bath or both, single or double vanity, storage, lighting, and power for hairdryers and heated rails. A clear list makes a clear quote.
What hides behind the old tiles
Most surprises in a bathroom turn up on the first day of demolition. Old showers leak slowly for years, and the floor framing, studs and linings behind them can be soft or rotten. Older homes may have asbestos in wall sheeting or floor underlay, which a licensed removalist must take out. Termite damage stops work until the area is inspected and cleared. Earlier work that was not done properly has to be put right before anything new is built on top of it.
None of this can be priced exactly until the room is stripped, so it sits in the contract as a provisional sum. If extra work is needed, we show you what we found and agree the variation in writing before it goes ahead.
Selections, tiles and fittings
Selections are where you have the most control. Tiles, tapware, vanity, screen, toilet, mirror and lighting are carried as prime cost allowances, and we point you to the local suppliers we use. Tile choice affects labour as well as supply: standard formats lay quickly, herringbone and other patterns take longer, and tiling floor to ceiling uses more tile and more of the tiler's time, though it saves painting. Spend on what is built into the wall, such as mixers and in-wall spouts, because replacing them means opening the tiles. Rails and mirrors are easy to swap later.
Waterproofing, done once and done properly
Waterproofing goes on after the framing, plumbing and sheeting and before the tiler starts. It is built to the Australian standard for wet areas, which sets how far the membrane runs up the walls and across the floor, with more coverage in the shower and on timber or upstairs floors. Ours is applied by a licensed waterproofer, cured for the time the product needs, certified and inspected before any tile goes down. Rushing a cure to save a day is how bathrooms fail, so the program allows for it.
Niches and showers
Almost every bathroom we build has a shower niche, and the time to plan it is before the frame is lined. A niche is formed between the studs, so the stud depth sets how deep it can be; measure your tallest bottles before you choose. Keep it out of the main spray, often on the wall opposite the shower head or opposite the entry, between waist and eye height. Size it to the tile so the cuts land neatly. In a block wall, a niche needs a false wall built out in front.
Shower details worth deciding early
- In a walk-in shower, put the head and the drain on the side away from the entry
- Place the mixer so you can turn the water on without standing under it
- Match the drain grate and screen hardware to the tapware finish
- Choose a frameless, pivot, fixed panel or open walk-in screen to suit the space
- Add a rail or hand shower for tall family members and easier cleaning
Living at home through the works
You stay in the house during a bathroom renovation, so plan around it. If there is a second bathroom, we keep it usable throughout. If there is only one, we plan the sequence and any temporary facilities with you so the time without a shower is as short as possible. Avoid school holidays and family events if you can, expect short water and power shutdowns while the plumber and electrician connect, and keep a clear path from the street for materials and rubbish. Order items with long lead times early so the tiler is never waiting.
Getting a real number
A real price for a bathroom comes from a site visit. Dani looks at the room, the floor structure, the plumbing and what he can see under the house or in the ceiling, and talks through your list. We then quote on a fixed-price QBCC contract: the scope priced in full, a prime cost allowance for each selection and a provisional sum for hidden damage, each explained before you sign. Bring a designer's layout if you have one; if not, we can connect you with the local designer we use.